On December 10, 2017, a solemn ceremony of commencement of construction under a Limited Construction Permit (LCP) issued by the Turkish Atomic Energy Authority (TAEK) in October 2017 was held at the Akkuyu NPP site.

 The event was attended by the Chief Executive Officer of Rosatom State Nuclear Energy Corporation Alexei Likhachev and the First Deputy Minister of Energy and Natural Resources of the Republic of Turkey Fatih Donmez.

Concreting the base of the facilities of the "nuclear island" is an important stage in the preparatory work. Under the Limited Construction Permit, construction and installation work is carried out at all facilities of the nuclear power plant, except for buildings and structures related to the security of the "nuclear island".

«Today, local residents are present at the ceremony, and I take this opportunity to tell you: «Thank you for your support!» Rosatom decided to establish the Akkuyu NPP Public Council for a permanent dialogue and joint participation in the project. We are standing at the starting point of a century-long cooperation, while the Akkuyu NPP will be providing Turkey with the clean energy» said Alexei Likhachev.


On December 2, 2017, the preparation of the base of the reactor building of Unit № 1 was completed. A Turkish company was engaged at the works and completed the job execution right on schedule.

In addition to the construction works on the site, environmental monitoring activities continue: seismological and meteorological parameters, groundwater and the marine environment are monitored on a regular basis. All works on the construction of the Akkuyu NPP are carried out in accordance with the Turkish legislation, with the direct participation and coordination of the Turkish Atomic Energy Authority.

The project offers significant opportunities for Turkish suppliers. According to preliminary estimates, the Turkish side will be able to accomplish about 35-40% of the Akkuyu NPP construction, which is equivalent to an amount of 6-8 billion US dollars.

More than 350 Turkish companies have applied for inclusion into the list of potential suppliers, the first of them have already received orders for the preparation of the infrastructure of nuclear power plant. To date, the total number of personnel on the site is more than 300 people, 90% of them are Turkish citizens, brought to the works from nearby areas of Büyükeceli, Silifke, Tasucu, Aydıncık.

Highly qualified engineering and technical support specialists from Turkish companies that had built the largest energy and industrial facilities of the Republic of Turkey have been invited to work.

In March 2018 AKKUYU NUKLEAR JSC is going to obtain a construction license, after which the base will be concreted, which is the official start of the construction of the first unit of the Akkuyu NPP ("first concrete" pouring).

 

For reference:
The project of construction of the first nuclear power plant in Turkey is implemented on the basis of the Intergovernmental Agreement signed between the Russian Federation and the Republic of Turkey in Ankara in May 2010. On October 13, 2011 TAEK gave AKKUYU NUKLEAR JSC a valid license for the site, and in November 2013 it approved the updated Ground Report on the site carried out by Akkuyu Nuclear JSC under the Site License Terms for the construction of the Akkuyu NPP with the installed capacity of 4,800 MW. On December 1, 2014, the Ministry of Environment and Urbanization of the Republic of Turkey approved the report elaborated by the Akkuyu Nuclear JSC on the Environmental Impact Assessment (EIA) of the Akkuyu NPP. On February 9, 2017, TAEK agreed on the parameters of the Akkuyu NPP site, and then on March 3, 2017, an application for a construction license was submitted to the Authority. On October 19, 2017, the company AKKUYU NUKLEAR JSC received a Limited Construction Permit (LCP from the Turkish Atomic Energy Authority (TAEK)), which was the first step towards obtaining a License to build a nuclear power plant.

The LCP allows to proceed to the arrangement of the pit of Unit № 1 before reaching the design level, the foundation construction of the base for the main and auxiliary facilities and constructions of Unit № 1, the vertical layout of the project site, backfilling of the Bay of Akkuyu to the level of +10.5 m, construction of freight terminals "Western" and "Eastern", construction of the eastern and southern drainage channels, construction of temporary buildings and structures, fire station, fire water tanks and fire pump station.

AKKUYU NUKLEAR JSC is a company established in 2010 to implement the Akkuyu NPP project in the South of Turkey in Mersin province. VVER-1200 Akkuyu NPP power units are among the most advanced generation III+ projects with enhanced safety systems that meet all existing requirements. This is a serial Russian project of a nuclear power plant on the basis of the project  Novovoronezh NPP-2 (Russia, Voronezh Region), the first unit of which was put into operation on August 5, 2016. After the construction of the Akkuyu NPP is completed, it will generate about 35 billion kWh per year. The lifetime will be at least 60 years

Σχόλια

Δημοφιλείς αναρτήσεις από αυτό το ιστολόγιο

Κελεύω δεν σημαίνει μόνο .....προστάζω-διατάζω

Αν ανατρέξουμε στην ΒΙΚΙΠΑΙΔΕΙΑ, στο λήμμα Κελευστής, θα διαβάσουμε το παρακάτω: Η λέξη «κελευστής» προέρχεται από το ρήμα κελεύω (προστάζω) . Αν στον ίδιο δικτυακό τόπο, ανατρέξουμε στο λήμμα Κελεύω, θα διαβάσουμε: 1.   Παροτρύνω-παρακινώ      2.   Διατάζω –παραγγέλλω     3.   Ζητώ-αξιώνω     4.   Παρακαλώ-ικετεύω Επιχειρώντας μια βαθύτερη προσέγγιση του όρου κελεύω και του αντίστοιχου βαθμού στο πολεμικό ναυτικό, Κελευστής, ανατρέχουμε, που αλλού;  στην αρχαία ελληνική γραμματεία και φυσικά στον Ξενοφώντα. Η Κρίστυ Εμίλιο Ιωαννίδου, συγγραφεύς και ερευνήτρια ναυτικής ιστορίας, στο βιβλίο της , ΛΕΞΙΚΟ ΑΡΧΑΙΩΝ ΕΛΛΗΝΙΚΩΝ ΝΑΥΤΙΚΩΝ ΟΡΩΝ  και  στο σχετικό λήμμα για τον Κελευστή, αναφέρει επικαλούμενη ως πηγή, το έργο του Ξενοφώντα (ΞΕΝΟΦΩΝΤΟΣ ΟΙΚΟΝΟΜΙΚΟΣ 21,3) Οι μεν των κελευστών δύναται τοιαύτα λέγειν και ποιείν,ώστε ακονάν τας ψυχάς των ανθρώπων επί το εθελοντάς πονείν!!! Αφήνω...

Τεχνητος πνιγμος

Ο τεχνητος πνιγμος ειναι μια παλαιοτάτη τεχνικη ανακρισης-βασανισμου. Ο ανακρινομενος τοποθετειται με κλιση πανω σε μια στερεη επιφανεια , δενεται σφιχτα και εν συνεχεια τοποθετειται στο προσωπο του μια πετσετα . Η συνεχης ριψη νερου δημιουργει το φαινομενο που διακρινεται στην κατω δεξια μικρη φωτο . Αυτη η κατακλυση με νερο των κοιλοτητων του κεφαλιου που συνδεονται αμεσα με την διαδικασια της αναπνοης , προκαλει ασφυκτικο φαινομενο και οχι μονο (ταχυκαρδιες), τα οποια εχουν και ψυχολογικες προεκτασεις εφοσον το θυμα υποβληθει σε συνεχη διαδικασια τεχνητου πνιγμου. Μελετες εχουν δειξη οτι και μετα 10 χρονια απο την υποβολη στην διαδικασια του τεχνητου πνιγμου τα θυματα εμφανιζουν πλεον των ψυχολογικων επιπτωσεων  πονους στο κεφαλι και πνευμονικες -αναπνευστικες διαταραχες. Ο τεχνητος πνιγμος αποτελει κομματι της εκπαιδευσης των αμερικανικων ειδικων δυναμεων, ενω σαν τεχνικη βασανισμου και ανακρισης εχει χρησιμοποιηθει απο τους Γαλλους στην Αλγερια, τους Αγγλους στην β.Ιρλ...

Ocean rig CRETE and AMORGOS

  The Ocean Rig Crete and Ocean Rig Amorgos will be the most advanced of Ocean Rig UDW's ultradeepwater drillships when delivered in 2018 and 2019.      Νέα μέλη στον στόλο της Ελληνικής                   εταιρείας                                           Ocean Rig Crete 7 th  Generation New integrated Design Deep Water Drillship. Ocean Rig TBN #1 is a new build and will be completed in Q1 2018. The rig is being built at Samsung Heavy Industries Shipyard in South Korea. The rig has dual activity capabilities and design for drilling operations in water depths up to 3650 meters (12000 feet). The rig is Dynamic Positioned, DP Class 3. ...