Today.....30/04/2018..... at the Black Sea coast of Turkey, the deep-water pipelay for Line 1 of the Turkstream offshore gas pipeline has been completed.
The average rate of the deep-water pipelay carried out by the pipelaying vessel Pioneering Spirit was 4.3 kilometers per day. The maximum pipelaying rate – 5.6 kilometers per day – was reached twice in February 2018.
In accordance with the schedule, the project is being simultaneously implemented on shore in Russia and Turkey and in the Black Sea. The receiving terminal is being constructed near the settlement of Kiyikoy, Turkey. Upon completion of the landfall sections the works on the first line will be completed. Following the works schedule, Pioneering Spirit will continue the deep-water pipelay of Line 2 in the third quarter of 2018.